Custom PTFE Lined Fittings RFQ Guide

Prepare drawings and purchase details for non-standard steel and PTFE lined fittings or pipe spools.

All procurement guides · By ZDPTFE

Content reviewed and revised:

DIRECT ANSWER

What should the enquiry include?

A useful custom PTFE lined fittings RFQ identifies the assembly, controlled drawing revision, shell material, requested liner, every flange or equipment interface, process medium, design temperature, pressure or vacuum, quantity, and required inspection documents. Separate fixed requirements from items open for supplier review so geometry, lining scope and commercial offers can be compared on the same basis.

Identify the lined assembly

A custom PTFE lined fitting is a steel shell and fluoropolymer-lined flow path specified as one assembly. Name the fitting or pipe spool, attach the current drawing and give the drawing number and revision. If the request starts from an existing installation, identify the matching equipment and the dimensions that cannot change. A photograph can explain the interface, but it cannot replace approved dimensions.

Show geometry and connections

Include nominal size, face-to-face dimensions, branch position, bend or transition geometry, flange standard and flange orientation. Mark any fixed bolt-hole orientation or equipment nozzle interface. For a group of spools, provide an isometric or line list that ties each drawing to its quantity. Ask the supplier to list unresolved dimensions before quoting a final configuration.

Define shell and liner separately

State the specified steel shell material and the requested PTFE or PFA lining. If the liner choice is open, describe the medium and operating conditions and request a proposal for engineering review. Identify any project specification or required document. Do not assume that two quotations with different liner, shell or flange scope are directly comparable.

Include service and inspection requirements

Provide the process medium, design temperature, pressure or vacuum, installation location and any cleaning or handling constraints. List the inspection, test, marking and documentation requirements actually needed for the project. The responsible engineer should confirm suitability and acceptance criteria for the complete assembly; a product category alone is not a service rating.

Compare the quoted scope

Request a quotation that names each drawing revision, component quantity, shell material, liner, connection details, inspection scope, exclusions and delivery destination. Separate sample or trial requirements from the planned batch. When a drawing or service condition changes, request a revised offer so pricing and technical assumptions stay aligned.

RFQ engineering checklist

  1. Name every fitting or spool and match it to one drawing number and revision.
  2. Show face-to-face dimensions, branch positions, orientation and fixed equipment interfaces.
  3. Specify the steel shell and requested PTFE, PFA or project-defined liner separately.
  4. State medium, design temperature, pressure or vacuum, installation context and quantity.
  5. List the required inspection, marking, packing and document deliverables.

Specification fields to prepare

FieldWhat to provide
Assembly identityComponent name, tag, drawing number, revision and quantity
GeometryNominal sizes, face-to-face dimensions, branch locations, bend or transition geometry
ShellSpecified metal shell material or project specification
LinerRequested PTFE, PFA or project-defined lining and facing scope
ConnectionsFlange standard, rating, facing, bolt-hole orientation and mating interfaces
ServiceMedium, design temperature, pressure or vacuum and installation constraints
AcceptanceInspection, test, marking, packing and document requirements

Applicability and limits

Use this guide for

  • Non-standard lined fittings
  • Drawing-based pipe spools
  • Replacement assemblies with controlled interfaces

This guide does not replace

  • Selecting a liner from a product image alone
  • Confirming service suitability without operating conditions
  • Replacing project engineering approval or an approved fabrication drawing

Inspection and document list

  • Drawing review record and approved revision, when required
  • Dimensional report for agreed interfaces
  • Material identification documents requested in the order
  • Agreed lining or assembly inspection and test records
  • Marking, packing and shipment document list

Request only the records needed by the project. Availability and final document scope must be confirmed in the quotation and order.

Review inspection and document scope for lined assemblies.

Source references

References define background scope only. A cited standard is not a statement of ZDPTFE certification or product compliance.

Related parts for your enquiry

Explore PTFE lined systems or prepare your quotation request.

Frequently asked questions

What should a replacement PTFE lined spool BOM include?

Give each spool a unique item tag, drawing revision and quantity. Identify both end connections, installed length, branch positions and orientation, then link the shell, liner and inspection requirements to that item. Mark any mismatch between the existing installation and the drawing for review before quotation approval.

Does a flange pressure class define the operating limit of a lined fitting?

A flange class alone does not establish the suitability of the complete lined assembly. Supply the medium, concentration, design temperature, pressure or vacuum, liner specification and connection details for project review. Confirm the agreed assembly requirements and applicable checks in the quotation and approved documents.

What drawing details are needed for a custom PTFE lined fitting?

Show the complete geometry, face-to-face dimensions, branch positions, flange or equipment interfaces, orientation, drawing revision and quantity. Identify dimensions that must match existing equipment.

Can a photograph replace the lined fitting drawing?

A photograph can explain the installation and existing interfaces, but it does not establish approved dimensions, shell and liner scope, flange details or acceptance requirements.

How should two lined fitting quotations be compared?

Compare the same drawing revision, shell material, liner, connections, inspection scope, documents, exclusions and quantity. Request a revised quotation whenever the technical scope changes.

Continue reading

Custom PTFE Parts RFQ Checklist

PTFE Machined Parts Drawing Requirements

Custom PTFE Parts from Drawing, Sample or BOM

PROJECT ENQUIRY

Have a lined fitting
or spool drawing?

Share the shell, liner, connection and service details available for your lined component enquiry.

Accepted:PDFDWGSTEPExcelImagesBOM
REQUEST A QUOTE ↗